February 2015 - Tender/Contract Sign
April 2015 - Pre-Construction exterior plans and variations
May 2015 - Interior selections, tiling variations
June 2015 - Demolition, Contract PA's quantified (hydraulics and sewer)
July 2015 - Continued... construction file estimation process, Site Supervisor assigned
- July 16th - Site Supervisor (Mark Smith) assigned and Construction file release
- July 22nd - SS Construction File pickup and review
- July 30th - Site Fencing and Peg out
- August 8/9th - Piering and leveling
- August 13-15th - Formwork
- August 17th - SLAB
- September 1st - External Plumbing
- September 10th - Timber Framing
- September 29th - Frames complete
- October 5th / 17th - Plumbing rough in and Water main connection
- October 30th - Brick Work Start
- November 17th - Scaffold / Week 3 Brickwork
- December 2nd - Brickwork 95% complete and brick cleaning
- December 4th - New Site Supervisor
- January 18th - Roof Installation
- February 5th - Upper roof tiling complete, cladding and eaves
- February 20th - Cladding complete and upper eaves, cladding and downpipes painted
- February 22nd - Scaffold dropped down to lower roof
- March 8th - Lower roof tiling complete
- March 17th - Electrical rough-in
- March 18th - Waterproofing
- March 23rd - AC indoor unit mounted. Welding of beams, priming, and frame straightening
- March 24th - Gas meter installed. Electrical service mains connected
- March 25th - Ceiling and wall Insulation delivered
- March 28th - Ceiling and wall Insulation installed
- March 30th - Plaster delivered
- April 1st - Plaster fixing
- April 2nd - Plaster edge/join/corner set
- April 16th - Rainwater tank installed and Garage Door
- April 19th - Stairs Installed (50%)
- April 30th - 25% Painting done
- May the 4th be with you - Kitchen, Laundry and Bathroom cabinetry installed
- May 10th - 50% Painting done
- May 12th - Kitchen and Vanity benchtops installed
- May 16th - Tiling starts
- June 18th - Tiling Complete
- June 27th - Stairs fully completed
- June 30th - Final plumbing fitout, Shower Screens, and internal painting 75%
- July 1st - Site fence removed
- July 14th - Walk in Linen, Pantry and Wardrobe fitout
- July 21st - Main bathroom vanity wall 're-tiled' due to crooked bulkhead
Hey here I read your post on Homeone and also find link to your blog here. After see your house ceiling and wall use Bradford Gold R3.5 just wonder what's R rate you use for interal wall studs? As we build with Coral homes and they use Bradford Gold R2.5 for ceiling and R1.5 for external wall. I think that quiet low rate. Also atm i want to add insulation for internal wall too but not sure what's R rate to go ? Many thanks
ReplyDeleteHi xiaoyi.
ReplyDeleteRawson provided wall 2.0 and ceiling 3.5 batts as standard. I think both are adequate, with my current house being 1.5 wall and 2.5 ceiling. I'm yet to experience the extra insulation ( clearly) , but the current house insulation is quite comfortable.