As we started this week, the brickwork has been completed to the first level. Extra bricks were delivered late last week and the green brick waste bin was swapped on Monday 16/11. More sand was also delivered in preparation for the next wave of work.
|
12/11 1st level brick work nearing completion |
|
12/11 Second delivery of bricks |
Yesterday, the scaffold was being erected. This will now allow the bricklayers to continue the upper level brickwork.
We received an update today from the SS, advising that the bricklayers expect to complete the brickwork within two weeks (weather permitting!). He also has lined up a brick clean, with fascia, guttering and roof tiles to follow.
We can now expect the eaves and cladding to be completed prior to Christmas. It will be a relief to know the site will be weather proof before the Christmas break. Fingers crossed the weather doesn't delay the schedule.
|
17/11 Scaffold delivery |
|
17/11 Scaffold installation on the western boundary |
|
17/11 Hive of activity |
No comments:
Post a Comment
Note: only a member of this blog may post a comment.