Links, Timeline and Other Information

Tuesday, 18 October 2016

Kitchen Dispute

Things were amicable and agreeable with the Supervisor up until we reached the end of the fix out stage with the build. That was, until the builder requested payment for the second last contract payment.
So lets disassemble how it started, and where it ended, so that those following along can not repeat several mistakes made here.

When the kitchen was installed on May 4th, and as you can imagine a very exciting day. The next day we had a closer look through the kitchen and found a major issue with the design.
Handle-less drawers are a poorly explained concept.
A handle less drawer can be constructed in several ways, but in the case of a melamine/laminate drawer front, is made using a shadow line concealed within the cabinet carcass.
As you can see in the images below (off centre) you can see the concealed 'L' behind the drawer front.

4/5 - 4 Drawer Set (Kitchen Island)

4/5 - 2 Pot Drawer Set (Cooktop Run)
So whats the problem?



SPACE. Lack thereof
14/5 - Cooktop 3 Drawer no.1 (9cm)

14/5 - Cooktop 3 Drawer no.2 (13cm)

14/5 - Island Bench 4 Drawer no.1 (8cm)

14/5 - Island Bench 4 Drawer no.2 (8cm)
There are some serious issues with the drawers, too shallow and unusable.

Kitchen Drawer 'not fit for purpose'

Many discussions and verbal assurances are made by the Supervisor to address the issue and amount to nothing. Over the following weeks we are patient and understanding of the 'busy time' the cabinetry and warranty team are experiencing. That is until we request closure on the matter prior to paying the fix out stage.
LESSON 1: Get everything in writing.
At this stage, we begin to explain in detail everything from the very beginning. The lack of consultancy in the kitchen design, no details on the 'signed plans' showing drawer elevations of internal height. Back and forward, push and pull.
Exasperated by this process, we consulted with Fair Trading and several others in legal matters as to what we could do. Fair trading logged our compliant in the last week of July and followed up with the Rawson the next week.
Both Fair Trading and the HoBAS recommended we make good on the contract payment, so we did. The claim and resulting pressure forced the construction manager to meet and discuss in person.
LESSON 2: Get advice. Call Fair Trading, Call NSW Home Building Advocacy Service.
LESSON 3: The contract is legal and binding. You must get good legal advice to the contrary if you wish to withhold payment. Consider very very carefully if you will not pay.
Our meeting with the construction manager was refreshing. We had a reasonable discussion, agreed to meet halfway in the costs and Rawson committed to rectify the issue quickly.
We received the variation and pricing on 11/8.

The kitchen was later fixed to our signed variation on the 2/9.
Once again, our amazing supervisor put on his tool belt and made sure things got done right the second time around. Without his assistance i doubt the kitchen installer would have done anything.











Monday, 25 July 2016

June/July Progress Update

Progress onsite over the last few months has been slow and frustrating.

The tiling took a long time to complete. The total time taken was a bit over a month. The tiling job was quite good, but the time taken has affected other installations such as the shower screens and plumbing. Not to mention the overall time added to our build!
18/6 Laundry complete

18/6 Master Bedroom Ensuite Complete

18/6 Master Bedroom Ensuite Shower


18/6 Main Bathroom

Shortly after the tiler completed his work, the plumbers returned to fitout the bathrooms.

30/6 Ensuite - Newbury 1675 Bath

30/6 Ensuite - Wall mount mixers and spouts
The final completion of the stair case railing! After more than 2 months, GENNERAL Stairs return to finish their work. Our railing was lost in an 'Admin' error.
27/6 Finally!

27/6
The Painters returned on the 30/6 to finish upstairs and start staining the timber work. Stegbar also turned up to install the show screens. The first of many problems to happen after this point as the frosted glass ensuite screen was incorrectly ordered.
30/6 Eden 4 1040W pivot

30/6 Study RIMM doors

30/6 Ensuite Shower Screen (incorrect glazing)

30/6 Main Bathroom Shower Screen
As the raw plaster sheets and timber skirting now have a coat of paint, the problems start appearing in the finishes such as bowed skirtings, and a bulkhead in the main bathroom is not square (nor is the vanity wall tiling!). Our issues register is getting bigger as we move along!

On a positive note though, the Site fence has been removed and the rubbish piles are disappearing.

1/7 Site fence removal
The month of July has pretty much been devoted to fixing issues on our list. Painters have been popping back every now and then touching up, patching, and sanding.
Bricklayers also came back to fix a few issues and replace some defective brickwork. Still waiting for another visit to fix up some areas before a final pressure clean.

10/7 Stair railing timber stained


10/7 Stair void railing stained

Monday, 16 May 2016

Internal Fitout progress

April has come and gone with not a huge amount of progress but incrementally the internals are getting ticked off.

The garage door was installed and glass panels in the large fixed windows installed on 15/4 ( one panel didn't make it over the stairs as it smashed into tiny grains of sand).
Rainwater tank installation and door/timber deliveries.
15/4 - Garage door (Colorbond - Surfmist)
15/4 - Garage door installed

15/4 - Internal Doors (Corinthian)

15/4 - Front door (Eden 4 1020 wide Pivot - Veneer finish)

15/4 - Caroma Newbury 1675 Bath x2

15/4 - 3500L Tankworks 'Evolution' tank

Genneral Stairs installed the Victorian Ash Closed Stringer staircase on 19/4. For some reason, they installed a temporary handrail and railing upstairs. Still no sign of when the final balusters and handrails will be installed. The stud frame needed to be removed as the opening for the stairs was incorrect.

19/4 Stairs

19/4 - Removed section of stud frame
Kitchen and bathroom vanity cabinetry was delivered on the 3/5, and later installed on the 4/5. The Kitchen is comprised of Finger pull /Shadow-line drawer sections with door and drawer facing based on Polytec Polar White -Sheen. The kitchen island face is Polytec Belgian Oak -Matt, with a 70mm thick drop down seating bench in the same finish which will be installed after the Cesaerstone bench is mounted.
NOTE: The bulkhead needed to be shortened due to the splashback window being lifted as it needed to match the finish height of the bench.

4/5 - Kitchen installed
4/5 - Kitchen (cooktop run/window splashback)
4/5 - Ensuite vanity & mirror board

4/5 - Main bathroom vanity & Mirror board

4/5 - Powder room (semi recessed) vanity & mirror board

Painting has been getting done over the last couple of weeks 'on and off' since the 30/4. The walls and ceiling have got some sealer coats, with more recent work on the doors and skirtings upstairs. The gloss top coats have been completed on the windows and doors.
10/5 - Main bedroom (painting progress)



The site was also cleared on the 10/5. All rubbish has been removed which now makes the house look alot closer to completion!
10/5 - Site clean!


Benchtops were later installed on 13/5, with sinks installed and the kitchen cooktop cutout. The kitchen bench and bathroom benchtops are 40mm and 20mm Caesarstone Osprey (respectively).
13/5 - Kitchen bench (Caesarstone 'Osprey')

13/5 - Powder room vanity (w/ Veda semi recessed sink)

13/5 - Ensuite vanity (w/ Veda counter top sink)

This week will see the start of the tiling, more painting and a front door! FINALLY!.
16/5 - Sand delivered for floor tiles