Another major milestone has begun onsite. The bricklayers have arrived on-site today to start the  masonary work. The team dropped off the mixer and barrows late yesterday, indicating an imminent start of the works.
I briefly met with the team this morning. Nathan and his team only just started the very first course as i arrived early this morning.
By the end of the day the team have made some amazing progress. 18-20 courses over a 10m section.
At this rate I'm seriously impressed.
|  | 