The tiling took a long time to complete. The total time taken was a bit over a month. The tiling job was quite good, but the time taken has affected other installations such as the shower screens and plumbing. Not to mention the overall time added to our build!
18/6 Laundry complete |
18/6 Master Bedroom Ensuite Complete |
18/6 Master Bedroom Ensuite Shower |
18/6 Main Bathroom |
Shortly after the tiler completed his work, the plumbers returned to fitout the bathrooms.
30/6 Ensuite - Newbury 1675 Bath |
30/6 Ensuite - Wall mount mixers and spouts |
27/6 Finally! |
27/6 |
30/6 Eden 4 1040W pivot |
30/6 Study RIMM doors |
30/6 Ensuite Shower Screen (incorrect glazing) |
30/6 Main Bathroom Shower Screen |
On a positive note though, the Site fence has been removed and the rubbish piles are disappearing.
1/7 Site fence removal |
Bricklayers also came back to fix a few issues and replace some defective brickwork. Still waiting for another visit to fix up some areas before a final pressure clean.
10/7 Stair railing timber stained |
10/7 Stair void railing stained |
No comments:
Post a Comment
Note: only a member of this blog may post a comment.