Onto the pics;
18/1 The crew arrive |
18/1 The majority of the tiles have been installed |
19/1 Second day |
19/1 Ridge capping getting finished |
This brings us to a major timeline event as our Site Supervisor has indicated that we are about 2 months from finishing now.
As we approach the next few weeks, we will have a carpenter lining the eaves and fixing the cladding on the upper level. A painter will also need to paint the eaves and cladding before the scaffold is finally removed.
As we are getting close to the final fitout stage, we are finalising plans for post handover works. These are ground floor tiling and carpet for the upper level amongst other things. I'll be posting separate items for these in the coming weeks for others considering these approaches themselves.